The 163-year-old Severn and Carno railway viaduct near Caersws is set to receive a much-needed facelift to prevent emergency closures along the Cambrian Line.
Buses will be replacing trains between Shrewsbury and Machynlleth from Saturday, May 6, to Sunday, May 21, as Network Rail carries out vital track and viaduct work
Passengers have been told work will continue after this 16-day-block in May but will be carried out during the night when trains aren’t running.
Jan Chaudhry-Van der Velde, Chief Operations Officer for Transport for Wales' rail services said: “We understand rail replacement services can be frustrating in the short term, but the overall benefits will be worthwhile for the future.”
The 70-metre-long timber viaduct was first constructed in 1860 and then reconstructed twice in 1906 and 1927. It connects the Cambrian Line over where the rivers Severn and Carno meet, holding up the single-line railway with its eleven spans.
READ MORE: Newtown railway station car park closes for a month
Network Rail and contractor, Amco Giffen, will completely replace timber beams on spans four, ten and eleven, while carrying out remedial work on the rest of the bridge, including the replacement of metallic straps and fixings.
Once complete, the work on the viaduct and the track will be done just in time for the busy summer period, ensuring regular passengers and those visiting the area will experience fewer delays and a more reliable service.
Preparation work has now started in Newtown and further west in Caersws before the work.
OTHER NEWS:
- Beloved sign directing people to Powys' international airport reappears
- Plans for two huge chicken farms left on hold as Welsh Government mulls intervention
- Powys woman breached order by threatening to cut off neighbour's power
Network Rail engineers alongside contractors, Colas Rail, will be working continuously around Newtown station to remove and replace the track to help make passenger journeys more reliable.
It includes 2,000 metres of new track, five new sets of railway points (which allows trains to move from one track to another) and 300 metres of new drainage (to prevent washouts and flooding).
Road-to-rail vehicles and unloading trains will be travelling from Abermule to Newtown station throughout the work. This work will help allow the new rolling stock from Transport for Wales to be able to use the station. During the work at Newtown, the station car park will be closed for a month so that we can carry out the work safely.
Buses will be replacing trains between Shrewsbury and Machynlleth from Saturday, May 6, to Sunday, May 21. Passengers are being asked to check www.journeycheck.com/tfwrail/ before travelling during this time.
Work will continue after this 16-day-block in May, but will be carried out during the night when trains aren’t running.
Gareth Yates, project manager at Network Rail Wales & Borders for Severn and Carno viaduct renewal, said: “This viaduct is over 160 years old so further work is needed to strengthen and extend the life of the structure to prevent emergency closures of the line.
“This work has been planned before the busy summer period, to minimise disruption to passengers visiting the stunning scenery along the Cambrian Line”.
Bradley Wallace, project manager at Network Rail Wales & Borders for Newtown track work, added: “We know that there is never an ideal time to carry out work on the railway and disrupt passenger services and we would like to thank the local community in advance for their patience whilst we carry out this essential track work.”
“This is a significant investment to the Cambrian line, and I hope local residents will bear with us as they can expect more reliable passenger services after this work.”
Jan Chaudhry-Van der Velde, Chief Operations Officer for Transport for Wales, commented: “This work by Network Rail will help make the railway infrastructure on the Cambrian line more resilient and improve the reliability of our passenger services. New Class 197 trains have been ordered for the line, so this investment will help clear the way for the trains to operate successfully.
“We thank our customers for their understanding and patience while this vital work is taking place.”
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here